Time and work aptitude questions with solutions: questions with worked answers

  1. 1

    A can do a job in 10 days and B in 15 days. How long will they take together?

    easy

    Time = ab/(a + b) = 10 × 15 / 25 = 6. Check: 1/10 + 1/15 = 5/30 = 1/6. Final answer: 6 days.

  2. 2

    12 men can finish a job in 10 days. How many days will 15 men take?

    easy

    Man-days = 12 × 10 = 120. Days for 15 men = 120/15 = 8. Final answer: 8 days.

  3. 3

    A does 1/3 of a job in 5 days. How long will A take for the whole job?

    easy

    1/3 of the job in 5 days means the whole job in 15 days. Final answer: 15 days.

  4. 4

    A and B together can finish a job in 12 days, B and C in 15 days, and A and C in 20 days. How long will all three take together, and how long would A take alone?

    medium

    Add the rates: 2(A + B + C) = 1/12 + 1/15 + 1/20 = (5 + 4 + 3)/60 = 1/5. So A + B + C = 1/10 and all three take 10 days. A = 1/10 - 1/15 = 1/30. Final answer: 10 days together, and A alone takes 30 days.

  5. 5

    A can finish a job in 20 days and B in 30 days. They work together for 8 days and then A leaves. How long will B take to finish?

    medium

    Combined rate = 1/12. In 8 days they do 8/12 = 2/3. Remaining 1/3 at B's rate 1/30 takes 10 days. Final answer: 10 days.

  6. 6

    A can do a job in 12 days and B in 18 days. They work on alternate days, A first. In how many days is it completed?

    medium

    Per two days: 1/12 + 1/18 = 5/36. After 14 days (7 cycles) they have done 35/36. Remaining 1/36 is done by A on day 15 in (1/36)/(1/12) = 1/3 day. Final answer: 14 1/3 days.

  7. 7

    A is twice as efficient as B. Together they finish a job in 12 days. How long does each take alone?

    medium

    Let B's rate be r and A's 2r. 3r = 1/12 so r = 1/36. B alone takes 36 days and A alone takes 18 days. Final answer: A 18 days, B 36 days.

  8. 8

    3 men or 6 boys can finish a job in 10 days. How long will 6 men and 8 boys take?

    medium

    1 man = 2 boys, so 6 men = 12 boys. Total 20 boys. The job is 60 boy-days. 60/20 = 3. Final answer: 3 days.

  9. 9

    A, B and C can do a job in 6, 8 and 12 days respectively and they are paid Rs 1,800 for it. Find each person's share.

    medium

    Rates 1/6 : 1/8 : 1/12 = 4 : 3 : 2. One part = 1,800/9 = 200. Shares: 800, 600, 400. Final answer: Rs 800, Rs 600, Rs 400.

  10. 10

    A can do a job in 8 days and B in 12 days. A starts alone and B joins after 2 days. In how many days is the job done?

    hard

    A does 2/8 = 1/4 in 2 days. Remaining 3/4 at the combined rate 1/8 + 1/12 = 5/24 takes (3/4) × (24/5) = 3.6 days. Total = 5.6 days. Final answer: 5 3/5 days.

  11. 11

    20 men can finish a job in 15 days. After 5 days, 10 men leave. In how many days in total will the job finish?

    hard

    Total = 20 × 15 = 300 man-days. After 5 days 100 are used, 200 remain. At 10 men this takes 20 days. Total = 25 days. Final answer: 25 days.

  12. 12

    A and B together finish a job in 6 days. A alone takes 10 days. How long does B take alone?

    hard

    B's rate = 1/6 - 1/10 = (5 - 3)/30 = 1/15. Final answer: 15 days.

  13. 13

    A can do a job in 15 days and B in 20 days. They work together, but A leaves 5 days before the work is finished. In how many days is it done?

    hard

    Let the total time be x. B works x days, A works x - 5 days. (x - 5)/15 + x/20 = 1, so 4(x - 5) + 3x = 60 and 7x = 80, x = 80/7. Final answer: 11 3/7 days.

  14. 14

    4 men and 6 women finish a job in 8 days. 3 men and 7 women finish it in 10 days. How long would 1 woman alone take, and 1 man alone?

    hard

    8(4m + 6w) = 10(3m + 7w) gives 32m + 48w = 30m + 70w, so 2m = 22w and m = 11w. Total work = 8 × (44w + 6w) = 400w. A woman takes 400 days. A man takes 400/11 = 36 4/11 days. Final answer: woman 400 days, man 36 4/11 days.

Frequently asked questions

What is the LCM method in time and work?

Take the total work as the LCM of all given times. Each worker's daily output then becomes a whole number, so you avoid fractions.

How do I handle workers who leave or join partway?

Track the portion of work finished at each stage and subtract it from 1 to find what remains.

How are wages divided?

In the ratio of work done. For equal time, that is the ratio of rates; for unequal time, it is the ratio of rate × time.

What is related to this topic?

Pipes and cisterns uses the same method, with inlets as workers and outlets as negative workers. The campus placement interview guide covers what follows aptitude.

Related guides

More in Aptitude Questions for Placements

See all in this section