Time and work aptitude questions with solutions
Last updated 2026-11-19
Time and work problems treat a job as one unit and each worker as a rate of progress per day. Once you think in rates, combined work, alternate-day work and wage sharing become simple arithmetic.
The page gives the formulas and 14 problems from two-worker questions to alternate working and man-days. If you want the same idea applied to tanks, see pipes and cisterns. For the overall plan, read how to crack an aptitude test.
Key formulas for time and work
- If A finishes a job in n days, A's rate is 1/n of the job per day.
- Working together: rate = 1/a + 1/b, so time = ab / (a + b).
- Man-days: Work = men × days × hours per day. M1 × D1 = M2 × D2 for the same work.
- Efficiency is inversely proportional to time taken. If A is twice as efficient as B, A takes half the time.
- Wages are shared in the ratio of work done, which equals the ratio of rates when everyone works for the same time.
- LCM method: take the total work as the LCM of the days, and each worker's daily work becomes a whole number.
Shortcuts and common mistakes
- Pick the total work as the LCM of the given days so that daily work comes out in whole numbers.
- For 'A leaves 5 days early' problems, let the total time be x and write A's contribution as (x - 5)/a.
- If three pairs are given (A+B, B+C, A+C), add them and halve to get A + B + C.
- Check an answer by confirming that the fractions of work add up to exactly 1.
Time and work aptitude questions with solutions: questions with worked answers
1 A can do a job in 10 days and B in 15 days. How long will they take together?
easyTime = ab/(a + b) = 10 × 15 / 25 = 6. Check: 1/10 + 1/15 = 5/30 = 1/6. Final answer: 6 days.
2 12 men can finish a job in 10 days. How many days will 15 men take?
easyMan-days = 12 × 10 = 120. Days for 15 men = 120/15 = 8. Final answer: 8 days.
3 A does 1/3 of a job in 5 days. How long will A take for the whole job?
easy1/3 of the job in 5 days means the whole job in 15 days. Final answer: 15 days.
4 A and B together can finish a job in 12 days, B and C in 15 days, and A and C in 20 days. How long will all three take together, and how long would A take alone?
mediumAdd the rates: 2(A + B + C) = 1/12 + 1/15 + 1/20 = (5 + 4 + 3)/60 = 1/5. So A + B + C = 1/10 and all three take 10 days. A = 1/10 - 1/15 = 1/30. Final answer: 10 days together, and A alone takes 30 days.
5 A can finish a job in 20 days and B in 30 days. They work together for 8 days and then A leaves. How long will B take to finish?
mediumCombined rate = 1/12. In 8 days they do 8/12 = 2/3. Remaining 1/3 at B's rate 1/30 takes 10 days. Final answer: 10 days.
6 A can do a job in 12 days and B in 18 days. They work on alternate days, A first. In how many days is it completed?
mediumPer two days: 1/12 + 1/18 = 5/36. After 14 days (7 cycles) they have done 35/36. Remaining 1/36 is done by A on day 15 in (1/36)/(1/12) = 1/3 day. Final answer: 14 1/3 days.
7 A is twice as efficient as B. Together they finish a job in 12 days. How long does each take alone?
mediumLet B's rate be r and A's 2r. 3r = 1/12 so r = 1/36. B alone takes 36 days and A alone takes 18 days. Final answer: A 18 days, B 36 days.
8 3 men or 6 boys can finish a job in 10 days. How long will 6 men and 8 boys take?
medium1 man = 2 boys, so 6 men = 12 boys. Total 20 boys. The job is 60 boy-days. 60/20 = 3. Final answer: 3 days.
9 A, B and C can do a job in 6, 8 and 12 days respectively and they are paid Rs 1,800 for it. Find each person's share.
mediumRates 1/6 : 1/8 : 1/12 = 4 : 3 : 2. One part = 1,800/9 = 200. Shares: 800, 600, 400. Final answer: Rs 800, Rs 600, Rs 400.
10 A can do a job in 8 days and B in 12 days. A starts alone and B joins after 2 days. In how many days is the job done?
hardA does 2/8 = 1/4 in 2 days. Remaining 3/4 at the combined rate 1/8 + 1/12 = 5/24 takes (3/4) × (24/5) = 3.6 days. Total = 5.6 days. Final answer: 5 3/5 days.
11 20 men can finish a job in 15 days. After 5 days, 10 men leave. In how many days in total will the job finish?
hardTotal = 20 × 15 = 300 man-days. After 5 days 100 are used, 200 remain. At 10 men this takes 20 days. Total = 25 days. Final answer: 25 days.
12 A and B together finish a job in 6 days. A alone takes 10 days. How long does B take alone?
hardB's rate = 1/6 - 1/10 = (5 - 3)/30 = 1/15. Final answer: 15 days.
13 A can do a job in 15 days and B in 20 days. They work together, but A leaves 5 days before the work is finished. In how many days is it done?
hardLet the total time be x. B works x days, A works x - 5 days. (x - 5)/15 + x/20 = 1, so 4(x - 5) + 3x = 60 and 7x = 80, x = 80/7. Final answer: 11 3/7 days.
14 4 men and 6 women finish a job in 8 days. 3 men and 7 women finish it in 10 days. How long would 1 woman alone take, and 1 man alone?
hard8(4m + 6w) = 10(3m + 7w) gives 32m + 48w = 30m + 70w, so 2m = 22w and m = 11w. Total work = 8 × (44w + 6w) = 400w. A woman takes 400 days. A man takes 400/11 = 36 4/11 days. Final answer: woman 400 days, man 36 4/11 days.
Frequently asked questions
What is the LCM method in time and work?
Take the total work as the LCM of all given times. Each worker's daily output then becomes a whole number, so you avoid fractions.
How do I handle workers who leave or join partway?
Track the portion of work finished at each stage and subtract it from 1 to find what remains.
How are wages divided?
In the ratio of work done. For equal time, that is the ratio of rates; for unequal time, it is the ratio of rate × time.
What is related to this topic?
Pipes and cisterns uses the same method, with inlets as workers and outlets as negative workers. The campus placement interview guide covers what follows aptitude.
Related guides
More in Aptitude Questions for Placements
- Time, speed and distance aptitude questions with solutions
- Venn Diagram Aptitude Questions with Worked Solutions
- Active and Passive Voice Aptitude Questions with Answers
- Averages aptitude questions with solutions
- Blood Relations Aptitude Questions with Solutions
- Boats and streams aptitude questions with solutions
- Calendar aptitude questions with solutions
- Clock aptitude questions with solutions
- Coding Decoding Aptitude Questions with Answers
- Compound interest aptitude questions with solutions
- Critical Reasoning Aptitude Questions with Explanations
- Cubes and Dice Aptitude Questions with Solutions